Ruwais 4th NGL Train Instrumentation Works

Client:Petrofac-GS / ADNOC Gas Processing
Location:Ruwais
Year:2010
Type:Construction

  Scope of Work

  • Complete instrumentation works including works in greenfield testing and pre-commissioning:
    • Installation of cable trays – 75 km.
    • Below ground and above ground cabling – 2,500 km.
    • Cable glanding and termination – 41,000 glands.
    • Installation of junction boxes and marshalling/system cabinets.
    • Calibration, installation, and pre-commissioning works for field instruments – 6,500 instruments.
    • Assistance during commissioning and performance testing.